01

Tuesday Morning

Facility: 625,000 sq ft

Duration: 2.5 months

Dismantle Scope:

  • 14,730 pallet positions of selective rack

  • 3 level pallet flow module

  • 45,000 sq ft mezzanine

  • 5,000 linear ft of conveyor, sorters, and gravity pack lanes

02

Under Armour

Multiple facilities: 750,911 sq ft

Duration: 8 Weeks

Dismantle Scope:

  • ​39,042 Pallet Positions

  • ​2,032 ft of floor-supported conveyor

  • 1,200 sq ft mezzanine

IMG_2860.HEIC

03

Crate & Barrel

Multiple facilities: 750,911 sq ft

Duration: 8 Weeks

Dismantle Scope:

  • ​39,042 Pallet Positions

  • ​2,032 ft of floor-supported conveyor

  • 1,200 sq ft mezzanine

04

Lipman Brothers

Multiple facilities: 750,911 sq ft

Duration: 8 Weeks

Dismantle Scope:

  • ​39,042 Pallet Positions

  • ​2,032 ft of floor-supported conveyor

  • 1,200 sq ft mezzanine

04

Breakthru Beverage

Multiple facilities: 750,911 sq ft

Duration: 8 Weeks

Dismantle Scope:

  • ​39,042 Pallet Positions

  • ​2,032 ft of floor-supported conveyor

  • 1,200 sq ft mezzanine